INTEGRAL - Workplan

Project Duration • Workpackages



Project Duration

1. April 2004 - 31. March 2007


Workpackages


WP No.

Workpackage title

Lead contractor No.


0

Project coordination

1

1

Methodological set-up

1

2

Data selection, simulation and acquisition

7

3.1

Design of (D)INSAR data processing methods

1

3.2

Design of altimetry data processing methods

2

3.3

Design of methods for SAR data fusion

7

4

Software development

4

5

Geometric processing of SAR data

4

6

Glaciological analysis and modelling

5

7

Field surveys & Quality control

6

8

Generation of INSAR value-added products. Integration of results

3

9.1

Demonstration of results. Technology transfer

8

9.2

Dissemination and implementation of results

9

9.3

Scientific collaboration with related GMES projects

1



Contractor No.

1:

Joanneum Research, Institute of Digital Image Processing

2:

Centre for Polar Observation and Modelling, University College London

3:

Laboratoire d'etudes en geophysique et oceanographie spatiales (LEGOS UMR 5566), Centre National de la Recherche Scientifique (CNRS)

4:

GAMMA Remote Sensing Research and Consulting

5:

ENVEO - Environmental Earth Observation Information Technology GmbH

6:

Norwegian Polar Institute (NPI)

7:

Scott Polar Research Institute, University of Cambridge

8:

Laboratory of Radar Studies, Institute of Radioengineering and Electronics, Russian Academy of Sciences

9:

Norwegian Water Resources and Energy Directorate (NVE)